Week 2 Piering and Plumbing
Piering completed on 15 May 2014. We had allowance of 80lm, however piering came in at 53lm. We should get a credit back, but that will go straight towards the soil removal fees.
Apparently we have 150tons to be removed. One cost I did not expect. So far we are about $11K up in extras since the electrical variation. Im hoping that is the last of the surprise variations.